Engineering, Procurement $ Constrauction of Sepehr-Jufair field consists of:
12 Vertical(FAHLIYAN) , Vertical (GADVAN), u horizental ( ILAM ) Wellheads facilities,
17 Flow Line,
3 Oil Gathering manifolds,
An ultimate oil collecting station entitle as '' Receiving Area '' and one P.L from ''RA'' to WKPU
Construction and pre- commissioning for Mechanical Works of Unit's 51,55,75 ( CDU/VDU, LPG1, LPG2) and inside Refinery utilites and Interconnection Unit's (35,45,96) in Abadan Refinery
On 17 June 2019, IGC finished the installation of F18 Platform in Foroozan Oilfield, (possessed in common with Saudi Arabia) located in the Persian Gulf, weighing 1200 Tons.
The F18 Jacket weighing 1800 Tons, transported from Qeshm yard and installed in Foroozan field in Persian Gulf Foroozan shared oil field with Saudi Arabia.
Transportation and installation of F18 topside deck will be started subsequently within a short time.